Utilities

Council committee opens a plug-in solar docket and sets community solar comment deadlines

The Climate Change and Sustainability Committee voted 3-0 on Monday to start a regulatory proceeding for small plug-in solar devices and opened a brief public comment period on how Entergy New Orleans will bill community solar subscribers, with replies closing Nov. 30. It then spent two hours on the transmission limits behind the May 2025 load shed.

Council committee opens a plug-in solar docket and sets community solar comment deadlines
Photograph by Infrogmation of New Orleans, via Wikimedia Commons (CC BY-SA 4.0)
City Hall seen from Duncan Plaza. The Climate and Sustainability Committee met at City Hall on Monday, opening a plug-in solar docket in the morning and hearing transmission testimony into the afternoon.

NEW ORLEANS: The City Council's Climate Change and Sustainability Committee opened a new regulatory docket on plug-in solar devices on Monday and gave the public a short window to comment on Entergy New Orleans' plan for billing community solar subscribers, advancing both resolutions by 3-0 votes at its Nov. 16 meeting.

Committee chair Councilmember Aimee McCarron presided, with Council President JP Morrell and Vice President Matthew Willard answering roll call and Councilmember Eugene Green joining during the presentations that followed. Both resolutions now go to the consent agenda of the full council's Thursday meeting.

New Orleans at night in February 2022. Transmission Day testimony returned repeatedly to the limits on importing power into the metro area and to the May 2025 load shed. File photograph.
Photograph by 2C2K Photography, via Wikimedia Commons (CC BY 2.0)
New Orleans at night in February 2022. Transmission Day testimony returned repeatedly to the limits on importing power into the metro area and to the May 2025 load shed. File photograph.

A docket for panels that plug into a wall outlet

The first resolution establishes a formal proceeding, with a procedural schedule, to decide what rules should govern small portable solar units of the kind residents plug in at home, known as plug-in solar or balcony solar. The devices connect directly to a standard household outlet, cost less than rooftop systems, are easy to install and generally do not require professional installation, according to the council's announcement of the meeting. The council notes that at least 30 states have approved or are considering policies for the devices, and 10 have already authorized their use.

The second resolution opens the comment period on the compliance implementation plan Entergy New Orleans filed on Oct. 19 for community solar consolidated billing. Under the plan, the council is asked to approve the utility's implementation approach, how its costs would be recovered and what would change in the program's rules. The committee set Nov. 24 for written comments and Nov. 30 for replies. One community solar project is expected to start operating before the year ends, and the committee urged parties to file early.

Transmission Day: the load pocket and the data center surge

The rest of the meeting was given over to the council's first Transmission Education Day, with presentations from Entergy New Orleans, the grid research nonprofit GridLab, the Midcontinent Independent System Operator and EDP Renewables North America, and a closing panel with the Alliance for Affordable Energy, the Union of Concerned Scientists and Entergy. The council's announcement framed the session around regional transmission planning, grid challenges in MISO South and the infrastructure an evolving energy system requires.

The Superdome at night. MISO presenters told the committee that data center load can connect in 18 to 36 months, while large transmission lines take seven to 10 years to build. File photograph.
Photograph by M.Fitzsimmons, via Wikimedia Commons (CC BY-SA 3.0)
The Superdome at night. MISO presenters told the committee that data center load can connect in 18 to 36 months, while large transmission lines take seven to 10 years to build. File photograph.

Members heard that the New Orleans metro area sits inside a load pocket with limited ability to import power from outside, so a set amount of generation must stay online inside the region. A GridLab engineer traced the May 25, 2025 load shed to the outage of a 500-kilovolt backbone line combined with planned and unplanned generation outages and hot weather, and noted that new transmission takes five to 10 years to build once approved. MISO presenters said its board is expected to take up more than $14 billion in transmission investment in December, with load growth accounting for roughly $4.2 billion of that total, and that approved data center load can connect in 18 to 36 months, far faster than large transmission lines can be built.

The committee's regulatory work continues on Thursday, when the two resolutions reach the full council, and in the comment file on the community solar plan, which closes to reply comments on Nov. 30.

Filed under: Utilities, entergy, solar, city-council, utilities, transmission, miso

Corrections
None to date. The Tribune corrects errors promptly and transparently. Read our corrections policy.
NOLA Tribune

More from Utilities

Tulane's Future of Energy Forum wraps Wednesday after three days of grid, data center and affordability talks

Tulane's Future of Energy Forum wraps Wednesday after three days of grid, data center and affordability talks

More than 150 energy leaders, policymakers and researchers spent Sept. 28 through Sept. 30 on Tulane's uptown campus, with the Tuesday session on power prices, data centers and grid affordability landing squarely on questions New Orleans is already debating.
NOLA Tribune · Sep 30, 2026
November ballot asks voters to let public money replace private lead pipes

November ballot asks voters to let public money replace private lead pipes

SB 228 would amend the constitution to allow public funding for finding and replacing lead service lines on private property.
NOLA Tribune · Sep 26, 2026
Council committee backs 4-year extension of Entergy's rate formula

Council committee backs 4-year extension of Entergy's rate formula

The plan would run through 2030 annual filings, alongside a $29 million battery-storage program and $13 million in Francine storm costs.
NOLA Tribune · Sep 23, 2026
NOLA TribuneUtilities